Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

Wellesley
473 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 01/09/2020 To be able to use it for BHA-handling, a hole was made in the protector.

Drilling Engineer


PDF


Edit


Wellesley
474 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 01/09/2020
Hit shallow gas at 331m, only 24m below 36″ conductor shoe. Killed with 1.50 SG kill mud. Drilled . . .

Drilling Supervisor


PDF


Edit


Wellesley
475 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 01/09/2020
Hit shallow gas at 331m, only 24m below 36″ conductor shoe. Killed with 1.50 SG kill mud. Drilled . . .

Drilling Supervisor


PDF


Edit


Wellesley
467 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 31/08/2020 More manual handling and time spent in addition to less efficient handling when not having all BHA . . .

Drilling Engineer


PDF


Edit


Wellesley
464 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 27/08/2020 No fill on 36″ hole wiper trip. Ran 30″ conductor, found 1m fill on bottom. Washed to bottom, picked . . .

Drilling Supervisor


PDF


Edit


Wellesley
465 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 27/08/2020 Good suggestion from Dolphin not to do this as in past fibreglass tubing has broken due to vibration . . .

Drilling Supervisor


PDF


Edit


Wellesley
463 – Wellesley

Borgland Dolphin Drilling Operational 6204/11-3
Schweinsteiger
Top hole 26/08/2020
Bentonite loaded onto rig in fjord but problems transferring from silos to surge tank in pit room . . .

admin


PDF


Edit


Wellesley
232 – Wellesley

Transocean Arctic Logistics Operational 35/11-21 S
Grosbeak West
Top hole 16/06/2020 Crane operator was unable to lift from supply vessel as basket was too heavy at one end due to 36″ . . .


PDF


Edit


Wellesley
252 – Wellesley

Transocean Arctic Drilling Operational 35/4-2
Songesand
Top hole 16/06/2020 When cement was in place and 10 MT weight was slacked off conductor to set it on bottom, noticed the . . .


PDF


Edit


Wellesley
255 – Wellesley

Transocean Arctic Drilling Operational 35/4-2
Songesand
Top hole 16/06/2020 The handling pup was 3 m which was not long enough to get the WH below rotary and get the tuggers up . . .


PDF


Edit