Operator Rig Discipline / Origin Project Phase Well Section Date What Happened

PGNiG
4907 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
17/09/2022 During bulking the boat was alongside and was covered in dust

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4905 – PGNiG

Deepsea Yantai Drilling Operational 6608/1-1 S
Copernicus
P&A 16/09/2022 To balanced the cement plug by pumping more spacer behind the cement plug.

Drilling Engineer / Morten Laget


PDF


Edit


PGNiG
4817 – PGNiG

Deepsea Yantai HSEQ
NEA Q&A
Planning 6608/1-1 25/08/2022

Hearing comment from the Norwegian Directorate of Fisheries
Fiskeridirektoratets oppgave ved slike . . .

Sanne Risbakk / Christina Sæland Rødne



PDF


Edit


PGNiG
4819 – PGNiG

Deepsea Yantai Drilling
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

Overburden Lithologi/Subsurface-prospektet 6608/1-1 S Copernicus i PL1017

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4820 – PGNiG

Deepsea Yantai Drilling
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

Well design and drilling operation with focus on risk assessments for each hole section,
including . . .

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4821 – PGNiG

Deepsea Yantai Drilling
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

Results from Blowout & kill study and input parameters from subsurface, including chosen
relief . . .

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4822 – PGNiG

Deepsea Yantai HSEQ
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

The question of how PGNiG relates to the fact that the estimated annual
probability of loss of MSF . . .

Sanne Risbakk / Ã…se Kristin Pettersen



PDF


Edit


PGNiG
4823 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

The question of how the operator (PGNiG) ensures that the site-specific
criteria set for . . .

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4824 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

How are the weather conditions monitored ?​

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4825 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

It is sometimes run with reduced power from auxiliary engines for operation of the DP to save fuel. . . .

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4826 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

Is there a permanent or site-specific approval from DNV with regard to waves in deck for survival . . .

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4827 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

At which combinations of significant wave height and period should one, according to the operation . . .

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4828 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 Other 25/08/2022

How is the wave height measured at the location?​

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4829 – PGNiG

Deepsea Yantai Marine
PSA Q&A
Planning 6608/1-1 S
Copernicus
Other 25/08/2022

Are there site-specific measurements of waves that make you know when to change draft?

Sanne Risbakk / Morten Laget



PDF


Edit


PGNiG
4763 – PGNiG

Deepsea Yantai Marine
Own Experience
Planning Copernicus Rig move 23/08/2022 Mooring analysis was requested at an early stage of the planning fase, but was not taken into . . .

Stian Engvik / Morten Laget


PDF


Edit


PGNiG
4764 – PGNiG

Deepsea Yantai HSEQ
Own Experience
Planning 6608/1-1 Other 23/08/2022 DSY waste management plan is according to IMO, and does not conflict with NOROG 093. It was . . .

Christina Sæland Rødne / Christina Sæland Rødne


PDF


Edit


PGNiG
4762 – PGNiG

Deepsea Yantai Drilling
Own Experience
Planning Copernicus Intermediate section 22/08/2022 4-string contingency scenario was miscommunicated and we did not have the 13 3/8″ SSRII landing . . .

Richard Mollison / Morten Laget



PDF


Edit


DNO
4761 – DNO

No Rig Drilling
Own Experience
Planning No well N/A 10/08/2022 In DG1-DG2 rig screening strategy the project landed on 1.5 or Dual derrick rig and all time and . . .

Zol Mollaeian / Sigve K. Næsheim


PDF


Edit


Wellesley
3246 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
P&A 29/01/2022
Cement plug was pumped without incident, POOH through cement was without incident. Circulated clean . . .

Drilling Supervisor / Morten Laget



PDF


Edit


Wellesley
2413 – Wellesley

Borgland Dolphin Drilling
Own Experience
Operational 36/1-4
Hemispheres
Surface section 04/01/2022
Ahead of a connection at 1146m (105m below the 13 3/8″ shoe), a blockage occurred in the cuttings . . .

Drilling Supervisor / Morten Laget


PDF


Edit